Entering Labor Units in P6

AB TimoMember for 15 years 3 months
Created
1
1
0

Hi There,

Suppose we have an activity havig Duration=10DAys,

Calender is 8hz/Day & 6 Days/week.

" 4 " Skilled Labors are required each day for the activity to complete.How will we assign the "Skilled Labor"resource to activity,

Please tell me which option is correct from following,

1. Will Resource of "Skilled" Labor be assigned Separately 4 Times  i.e 8h/Day ,4 times.each time showing one Skilled Labor and "4" times showing 4 labors.    Or,

2. We will assign Resource of "Skilled Labor" Collectively  i,e 4*8=32 h/Day???

1 reply

Oldest first
  1. 0
    AB Timo ·

    i forgot to mention that I am

    i forgot to mention that I am using Primavera P6

Log in or join to reply