Deleted Tasks (WBS) by Principal

Roland PayawanMember for 23 years 4 months
Created
1
4
0

Hello Everyone,

We are advised by the Principal to delete a group of activities/wbs from the Programme and I'm wondering which is the best way to delete it.

First - Delete/dissolve the group of activities completely including all the assigned resources that will change the periodic and cumulative planned (%) percentage that is previously approved or

Second: mark the group of activites 100% complete so that the previosly established planned weight won't be changed.

I'd love to hear any suggestion from you guys.

Thanks in advance and happy planning.

1 reply

Oldest first
  1. 0
    Shah. HB ·

    Hi Roland Payawan Which

    Hi Roland Payawan 

    Which software you use ?

    In p6 deleting WBS will delete activities under it

     

    Cheer's

    Shahul