UAE Labour Indices

Alan McMahonMember for 14 years 11 months
Created
1
2
0

Is anyone able to direct me to Labour Indices for the UAE, or, a correction factor to apply to UK / Western rates such as those provided on this website.

I'm initially interested in Excavation to pile and pile breaking.

 

Any responses greatly appreciated.

 

Regards

1 reply

Oldest first
  1. 0
    Ernesto Montales ·

    Allan,   Based on my own

    Allan,

     

    Based on my own experience working in Dubai from 2005 to 2007, if I can remember it correctly, I'm getting around .40 to .60 thats based on an overall view.

    Hopes this helps.

     

    Regards,

     

    Ernesto

     