I recently built a schedule in P6 that had an must end by date of July 23, 2012.

Shortly there after, additional work and time was added to the project.

How can I add the 6 extra weeks to my schedule?  I need to move the must end by date out by an additional 6 weeks.

Thanks,

Dave

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Dave,   From Enterprise >

    Dave,

     

    From Enterprise > Projects, highlight the relevant project.

    Then go to View > Show on Bottom > Project Details

    Go to the "Dates" tab of the Project Details, and you can ammend your Must Finish By date here.

     

    Cheers,

     

    G