Changing the Data Date and its Impression on Project Milestones

Ed AfkhamMember for 15 years 2 months
Created
1
3
0

 

Changing the data date shouldn’t practically push back project milestones.

How do you justify that considering the fact that it pushes back not started activities the same period of data date? 

1 reply

Oldest first
  1. 0
    Forrest Chen ·

    Hi,If it is the first

    Hi,

    If it is the first activity (normally a start milestone), then you need to give it a contraint as 'start on';

    as for other activities, you can either constrain them (not recommended) or logically link them together.

    Hope the above helps with you question.

Log in or join to reply