Dear Seniors,

 

Can you please advise how Performance % complete works in P6? Thanks

 

Regards,

BIM

4 replies

Oldest first
  1. 0
    James Buxey ·

    Hi   Performance % complete

    Hi

     

    Performance % complete is a 'roll up' of all EV earned through Physical % complete

    Ie if you have a number of tasks that collectively add up to a EV £100 and the total budget is £1000 the Performance % complete is 10%

     

    Hope this helps

     

    Regards

     

    James

  2. 0
    Ravirg Gehlot ·

    Preformance % comp. work only

    Preformance % comp. work only if your schedule is cost loaded ...

  3. 0
    Anning Sofi ·

    Performance complete is a

    Performance complete is a function of actual cost in relation to cost at completion in a cost loaded programme, generally used for EV analysis.  It can be on activity level or at summary level.The performance complete value is usually the activity %complete value. (Not the unit%, duration% or physical %).Also, the values in the performance complete are stored whenever you execute the store project performance function.

  4. 0
    Planner Bim ·

    Thanks for your

    Thanks for your guidance.

     

    Regards,

    BIM