the baseline
- Created
- 1
- 3
actualy i made the baseline according to the B.O.Q but somet times the B.O.Q is unbalanced in the (quantity & price) so all what i estimate of (cash flow or material or manpower)become wrong
i think that i should make 2 baselines (one according to the B.OQ and the other according to actual surveing) is it right or wrong
when i make update some times the actual quantity and the actual price become more than the planned quantity and price so how can i represnt this defference because there is no coloumn in the resources (actual cost/unit) and when i put quantity more than the planned the program automaticaly change the planned quantity to be actual