Skip to content

Resources

Hlamalani BaloyiMember for 14 years 8 months
Created
0
5
0

According to our contract with our client, We should not exceed 200 (men) resources at any given time. However when i extract information from Primavera to do my resource Histogram I get more than 200 (men) resources. If i get more than 200 (men) resources i must level these resources to be less than 200 (men) resources. My problem is how do i level these resources on my schedule? in my schedule i have a completion milestone which does not move as it is a constraint. so how do i level these resources?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?