Problem with importing resources in P6

Prince RajuMember for 7 years 3 months
Created
3
5
0
Good day!

 

I have a small query...please help me to resolve it if you can

When I’m importing a project in P6, resources(budgeted labour units) are not showing the same value as per the imported project.

Awaiting your replies

 

Thanks in advance 

 

Prince Raju

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    make sure that calculate cost

    make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked

  2. 0
    Prince Raju ·

    yes..its done.but still the

    yes..its done.but still the same issue

  3. 0
    Zoltan Palffy ·

    make sure that durgin the

    make sure that durgin the import process thet you select modify then for the resource select insert new

Log in or join to reply