Daily Qtys - P6

Luke CharetMember for 17 years 1 month
Created
0
2
0

Morning All,

Is it possible to add daily qtys into P6. Our engineers enter daily qtys into a spreadsheet and I would like to track it in P6. I am currently focused on tracking of crushing - I update the programme weekly and P6 spreads my qty evenly as an actual however I would like to add my daily qtys manually. Not sure if you can do it and some will argue is it worth it. However it sits on the critical path and I would like to manage it more closely.