External Relationships in P6v8
- Created
- 0
- 2
Attention fellow Planners, I need help to fix our level 3 construction schedule development in P6. The situation is described below:
1) There is 3 project files involved as follows:
File 1: Current EP Schedule @ Production Node
File 2: Update/Back-up EP Schedule for Month April @ Update Node
File 3: Level 3 Const Dev't Schedule @ Development Node
NOTE: File 1 has the same activities/ activity ID's with File 2 (only different data date File 1 having the latest data date)
2) At present, File 3 has external relationships from File 2 as its predecessor
3) I need to change the File 3 external relationships from File 2 to File 1.
4) Is there a faster way to change each activities external relationships/ predecessors? not going through each activity one by one?
5) There must be a way to change the Project ID of my external relationships so it would shift to the latesr EP but I have no idea how to do this.
6) Need help badly, and thanks in advance.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?