External Links in p6 Schedule need removing - inter project links

Mark GriffinMember for 20 years 4 months
Created
3
3
0

So i have opened my schedule today in p6 and relised someone else has copy parts of my project into their's as they needed the same type of activities in there schedule.

 

However when they have copied and pasted the WBS it they seem to have had the Only between copied activiies un checked (in the copy activity options) and thus i now have hundreds of inter project links as it is maintaining those links from my schedule.

 

How can i quickly removed these as there are hundreds

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have several

    you have several options

    Option 1  go to tools schedule 

    select options

    then select ignore relationships to and from other projects

    option #2

    filter for all activities

    right click columns 

    expand the dates availability on the left and choose

    External Early Start and also choose External Early Finish

    now in the External Early Start column Blank out the dated 

    now do a fill down a

    Now do the same thing for the External Early Finish Column

    Option #3

    go to tools

    global change

    New (on the right)

    Where  (leave this line blank)

    then

    External Early Start = (leave the rest of the line blank)

    and

    External Early Finish = (leave the rest of the line blank)

    then on the right select change

    then commit changes

     

    what ever option that you choose make sure to run the schedule calculations after you run your option

  2. 0
    Ghulam Haider ·

    Dears,I have copied part of a

    Dears,

    I have copied part of a network in another schedule which already have the same predecessors and successors. now the problem is that the imported activities relationships are still linked to the previous project. how can I determine all these external links and connect them to this schedule?

    Thanks in advance... 

  3. 0
    Zoltan Palffy ·

    create a new post to not glam

    create a new post to not glam on to an existing post but my answer is teh same to you add the columns for external early start and external early finish to see which ones these are also any external linkes activity will have an astericks at the end of the date column that indicates that it is a constrained activity 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?