Problems Importing between 8.0 and 7.1
In the Open Standard
Aidan KellyMember for 15 years 5 months
- Created
- 0
- 2
0
Hi All
I just arrived on a project where they are using P6 8.0.
As I only have 7.1 on my machine the planner exported a xer file in 7.1 so i could view the schedule.
When i do a resource report there are some discrepancies.
If i run RA-01 Resource Assignments report in certain cells the figures will be staggered. e.g the description will be in the planned units cell the planned units in the planned start cell etc.
Any ideas why this may be happening?
Thanks in advance.
Aidan
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?