Skip to content

Problems Importing between 8.0 and 7.1

Aidan KellyMember for 15 years 5 months
Created
0
2
0

Hi All

I just arrived on a project where they are using P6 8.0.

As I only have 7.1 on my machine the planner exported a xer file in 7.1 so i could view the schedule.

When i do a resource report there are some discrepancies.

If i run  RA-01  Resource Assignments report in certain cells the figures will be staggered. e.g the description will be in the planned units cell the planned units in the planned start cell etc.

Any ideas why this may be happening?

Thanks in advance.

Aidan

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?