Skip to content

Setting up a 9//80 Calendar with Primaver v7

Katie MorrisMember for 14 years 4 months
Created
0
3
0

Our construction crews have switched calendars mid project.

The original calendar was a Monday-Friday 8hr/day calendar.

The new Calendar is a 9/80

For those not familiar with a 9/80:

Week 1 Monday - Thursday 9hrs, Friday 8hrs and on

Week 2 Monday - Thursday 9hrs with Friday being a non work day.

 

My question pertains to how do I go about setting this calendar up in my project.

I will need to apply it to my remaining activities only.

I have created a calendar to modify, however, I get stuck on filling in the Time Period Units (hrs/day, hrs/week, etc)

I am fairly experience in using Primavera, however, this issue has me confused.

THank you for your help.

 

Katie

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?