Dates in P6
In the Open Standard
Lacey ThomasMember for 14 years 4 months
- Created
- 1
- 2
0
Hello -
I am working on a schedule and I have some actuals, but then there are dates that don't have actuals and they are getting pushed out by the data date even though they have relationships that should push them out months after the data date? Any ideas on how to fix this?
Thanks!
1 reply