I understand that upon approval of baseline, it seves as a contractual document.

How about S curve and Manpower histogram ? Does it constitute of a committment to comply with the manpower, equipment and performance aspect?

Does it work against us if the actual deviate too much from the planned ?

And does it relate to acceleration cost calculation etc?

1 reply

Oldest first
  1. 0
    Saju TS ·

    DearThere are two types of

    Dear

    There are two types of progress measurement a) Based on man days  b) Based on cost

     S curve is basically progress measurement , for that you have to load man days or cost in order to generate  S curve

    Base line is a program plan that include man pwer plan, machine plan, and cost plan, it is basically for measuring deviation from actuals.

    If there is deviation, next program is a recovery program with more productivity ( more resource and less time).

    How ever the loading is purely depeds on the client consultant, or internal reporting need