Skip to content

Cumulative late curve

Sunil BabuMember for 15 years 11 months
Created
4
3
0

Dear All,

How can we generate a cumulative late curve from the resource usage spread sheet

in P6. Your valuable remarks are highly acceptable..

Regards.

Sunil.

4 replies

Oldest first
  1. 0
    Wynand Jonker ·

    I will put a finish as late

    I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps.

  2. 0
    Mike Testro ·

    Hi Wynand Why not just add

    Hi Wynand

    Why not just add the day total float to the ASAP date.

    Best regards

    Mike Testro

  3. 0
    Sunil Babu ·

    Hi Mike, Thx for this info...

    Hi Mike,

    Thx for this info...

  4. 0
    Sunil Babu ·

    Hi Wynand, Thx for this

    Hi Wynand,

    Thx for this info..

    Sunil.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?