Merging Multiple projects into one project

Sm PumMember for 14 years 11 months
Created
2
2
0

Hi;

I have got separate schedule for Procurement,mobilization and construction from our sub-contractors.How to make these all as one project?

 

Regards

2 replies

Oldest first
  1. 0
    Sm Pum ·

    Primaver P6  Regards

    Primaver P6 

     Regards

  2. 0
    Faraz Memon ·

    Hello SM Pum, This is

    Hello SM Pum,

    This is actually very easy,

    1 - Go to import utility and select the file type.

    2 - Tick Project

    3 - Select the Destination File

    4 - In the "Import Project Options" phase, select "Add into existing Project" in "import action" list and choose your project in the "import to" list.

    5 - you can can only add the xer files to a wbs, so make a wbs for each file you want to import.

     

    I Hope it helps :)

     

    Regards,

    FM