Man Power Histogram from actuals
In the Open Standard
Saju TSMember for 17 years 3 months
- Created
- 0
- 2
0
Dear all
I prepared a man power histogram from actual dates ( actual start and expected date to finish ). there are activities alredy started and compleated 50% and consumed 50 % of man power, but the generated man power histogram not showing any reduction of man power in started activities . I really want to filter the consumed man power from the activity and show a realistic histogram , please give your suggestions to create a man power histogram in P3 by filtering man power that already consumed
thanks
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?