Man power Productivity

Arun VasanthMember for 17 years
Created
13
7
0

Dear Friends

It will be highly appreciated if you will be clearing my doubt ASAP.

Eg .I have a task of block work of Quantity  400 M2 .

Kindly clarify the production in the attached picture .

2.5 M2 per Hour means it is the production rate of one mason ???/Thn what is the propotion of helper .Kindly  give me the global propotion of Labour with the masons (block,plaster,shuttering,Steel fixing what ever).And also Please compute me the Block mason with the helper for the above quantity....

Regards

Arun

13 replies

Oldest first
  1. 0
    Rafael Davila ·

    m2/mr means some production

    m2/mr means some production rate per hour for a crew that can be a mason plus a helper

    m2/m-hr would be production rate per man-hour

    Production rates without crew description are misleading, even per man-hour, you might have several production rates depending on the crew composition. It is not the same moving dirt with a 10-cm truck than with a 20-cm truck for one hour or one man-hour. It is not the same placing concrete with a wheelbarrow than with a 90-cm per hour concrete pump that can swallow several concrete trucks in an hour with ease, two chutes side by side so there is no waiting between trucks.

  2. 0
    Mike Testro ·

    Hi Arun The most precise way

    Hi Arun

    The most precise way to get production rates for your project is to look at the tender breakdown.

    The individual rates should be set at Labour - Plant - Material.

    The money can be converted to hours using the labour rate per hour.

    If there is no individual labour rate then apply a reasonable labour percentage - 35% to 40% for blockwork

    You should also take account of the other items related to blockwork productivity:

    Openings and lintels

    Angle head restraints

    M&E Openings

    Fire Proofing etc.

    These should all be added to the blockwork hours and then allocated pro rata to your programme tasks.

    Best regards

    Mike Testro

  3. 0
    Nanding D. ·

    Hi Planners, Production rate

    Hi Planners, Production rate in Planning Planet is great, but I think it will be more meaningful if the Production Rate will be associated with basic Crew Description and Equipment Detail. Thanks, Nanding
  4. 0
    Arun Vasanth ·

    Dear FriendsIam Supporting

     

     

    Dear Friends

    Iam Supporting Nidan...

    We planners have to prepare a production rate based on the manpower using..

    for eg 1000 m2 block work 

    10 Block builders its propotion of helpers..

    If any body have please share...

     

    Arun

  5. 0
    Arun Vasanth ·

    Dear Friends I got the

    Dear Friends

     

    I got the Productivity rate from a Engineer who  is silent the Forum (Mr.Pinan).

    Iam very thankful to Mr.Pinan.

    If any body wants  the productivity with Crew Please post their email ID...

    This productivity we can use for  GCC Only....

     

    Regards

    Arun  

  6. 0
    Rafael Davila ·

    http://www.escsi.org/uploaded

    http://www.escsi.org/uploadedFiles/Technical_Docs/SmartWall_Masonry/3700.4%20Estimating%20Production%203-95.pdf

    Without drawings and specifications you cannot make a good estimate, it is not the same for different block size, not the same production rate for blocks to be installed on the ground than for blocks to be installed using scaffolding. Also the vertical and horizontal reinforcement matter. That is why most companies do not outsource scheduling unless the specifications call for a scheduling software they do not know. It is a pity industry have not realized that scheduling should be done in-house, by the team that will be in charge of the means and methods. We have some specifications that even require the contractor to hire an external scheduler to use their particular software choice, unbelievable but true.

  7. 0
    Edison ·

    Dear Mr. Arun, Please send me

    Dear Mr. Arun,

    Please send me the productivity rates at use private message service

    Regards,

    Owais

  8. 0
    Justin James ·

    Hello Mr.Arun,Can i have a

    Hello Mr.Arun,

    Can i have a copy as well my mail is sjustinjames@gmail.com

    Thanks & Regards

    Justin

  9. 0
    Shaik Yakub ·

    Hi can u plz send me a copy

    Hi can u plz send me a copy on yakub_sky@yahoo.co.in or yakub.sky@gmail.com

     

    thanks in advance

    Regards,
    Shaik

  10. 0
    Shaik Yakub ·

    HI Arun   Can u plz send me a

    HI Arun

     

    Can u plz send me a copy to yakub_sky@yahoo.co.in or yakub.sky@gmail.com

     

    Thanks in advance,

     

    Regards,

    Shaik

  11. 0
    Dura Cell ·

    Dear Mr.Arun,Please send me

     

    Dear Mr.Arun,

    Please send me a copy as well my email is d.cell@yahoo.com

    Thanks in advance

    Dura

  12. 0
    Dura Cell ·

    Dear Mr.Arun,Please send me

     

    Dear Mr.Arun,

    Please send me a copy as well my email is d.cell@yahoo.com

    Thanks in advance

    Dura

  13. 0
    Gary Whitehead ·

    Dear All: If anyone wants the

    Dear All:

    If anyone wants the productivity info from Arun, please send him a private message with your email ID (click on the little envelope next to his name).

    I'm locking this thread before it becomes full of begging letters.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?