Resource leveling breaks the CPM relationships?
No it is just the traditional CPM calculations will not keep the activities together.
Just model the sample job using any software and you will find out the activities you expect to occur in parallel might not occur as expected, it is enough for at any given time the lack of resources delays the incidental activity using FS and FF links, not to say if using a single link. If this happens then the predecessor should be delayed as to occur in parallel but this is not how CPM model works.
The following figure will give you the data for availability and assignment of resources plus the logic required to make the model using your software.

Note there are 2 form slab crews while there is only one reinforcing steel crew.
Using Spider Project you can model the schedule using separate activities in combination with strict links as follows and will yield expected results on this simple schedule. I doubt MSP or any Primavera product has such functionality but it wold be interesting to run the test.

Still I am reluctant to use strict links because they apply to resource leveling only and it might be that at some point some non driving logic link becomes driving a condition that might break the "strict" link delaying the successor but not keeping the predecessor in parallel. I play it safe and keep the crews assigned to a single activity and use the strict links functionality with much care only when assigning the different crews to the same activity is not feasible..
It is true you can work it out correctly but single activity is safer. In addition if you transfer the model to other software lacking strict links functionality it might spell disaster. Another issue is that strict links are limited to a single outgoing link per activity and in the case you need to model more than two related crews it will not make it. This can be solved bu linking SS related activities in tandem instead of one to many but can be error prone if not done with care.