Problem with baseline incluing actual date

Amir MinaMember for 19 years 3 months
Created
1
3
0

Dear All,

Plz help

I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned ..............

Regards,

Amir

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Assuming you are using

    Assuming you are using Primavera?

     

    This sounds like the classic issue of planned dates vs actual.

     

    Paul Harris has done an excellent presentation explaining how this works:

    http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf

Log in or join to reply