Units (Work) without Resources
- Created
- 0
- 4
I've noticed that in both P6 and MSP, values for Units (Work) are generated by assigning a Resource.
It's also possible to it is possible to directly enter a value for Units (Work) without assigning a Resource.
The latter method seems to behave much better when extending/shortening planned durations.
Both methods contribute to the 'cumulative units' outputs that are possible with P6 and MSP.
Is there any reason why I would want to generate my Units by assigning a resource, if I don't plan on doing any resource levelling on this particular schedule?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?