Level of Effort % Complete
- Created
- 0
- 2
Hey Guys,
I have a question about Level of Effort. I am using P6 v8.2.
I am trying to get the level of effort to update the % complete as the linked activities are updated but can't seem to get it to work. I have reviewed the forum for similar topics and have tried everything relevant that I found. Setting % complete type, relationship types (SF, SS, FF...).
I built a new simple project with a LOE and with 3 assigned activities. I have tried linking in different orders, setting % complete type to Physical, Units & Duration. No matter what I do the LOE % complete (or activity, units or any other % complete type) will not change as activities are updated. I also tried to create a start and finish mileston, linking the activities and the LOE back to those. Everything is manpower loaded with costs. What am I missing?
Thanks for feedback.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?