S curve in excel

Peter MayMember for 14 years 8 months
Created
4
3
0

Hi Guys I need your assistance

Quick question please, I  am trying to draw an S curve from P6 data showing early and late start together with actual

In the resource assignment option of P6, under display - spreadsheet fields  -Customise, what are the options I need to extract into my selected options field in order to be able to do this.

 

 

  

4 replies

Oldest first
  1. 0
    Pethanna Rajendran ·

    send me the data. let me see

    send me the data.

    let me see if i can help u!

     

    regards

    Pethanna.

  2. 0
    Raymund de Laza ·

    Peter, Look at the

    Peter,

    Look at the image...

     

  3. 0
    Rafael Davila ·

    Just remember that because of

    Just remember that because of poor handling of period performance in all Primavera products, in order to get reliable distribution of past performance data you will have to manually keep updating your period performance, you will need to establish your financial periods and then you will be able to get reliable past performance curves.

    This was an issue especially with Primavera Suretrak that do not even provided the financial periods workaround.

    This flaw is due to the way performance data is stored in all Primavera products. It is due to the distribution of performance data (resource hours and cost) for started but not completed activities.

    http://www.simplexgroup.com/oracle-primavera-p6-storing-period-performance/

  4. 0
    Johannes Vandenberg ·

    Hi PeterI use different

    Hi Peter

    I use different options for displaying s curves and of the early start and late start activities.

    >>The 'on screen'' option

    Primavera uses many options to display recourses in the spreadsheet tabulation and in the histogram and s-curve . I guess that these are familiar to you. I have not managed yet to transfer  these directly to a spreadsheet but on screen and for printing theses are good  reports.

    >> The 'assignment' option

    In the assignment, on the left hand part of your screen, you can easily, with filters and group and sort functions, create the information you require to make the s curves. These can be copy and paste into a Excel spreadsheet.

      >> The 'reports' option

    In the 'report' option you can create many different reports. These are particular useful if you are using standard reporting on a regular basis. I use this for the monthly portfolio manpower histogram and recourse assignment. These can be regular tabular reports but these can be downloaded in a spreadsheet and make the curves you desire.

    Regards

    Johannes 

     