Retroactive Adjustment order

Betsy JosephMember for 15 years 11 months
Created
2
2
0

For an LSTK contract, if an item is deleted from the Scope of work, after the Contractual completion date, is the Adjustment order retroactive???  Actual completion certificate has not yet been issued

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Betsy An ommission of work

    Hi Betsy

    An ommission of work from the agreed scope will not normally reduce the time for completion.

    However an adjustment can often be made if there is a claim for extension of time in place.

    Best regards

    Mike Testro

  2. 0
    Betsy Joseph ·

    Hi Mike, This omission of

    Hi Mike,

    This omission of work as you rightly pointed out, doen't have a time impact. The proposed Adjustment order is for the Cost impact only. Since it is a deletion, I personally feel that this is not retroactive.

     

    Regards

     

    Betsy