How can I incorporate change orders in the schedule?
In the Open Standard
Dimple DeanMember for 10 years 11 months
- Created
- 2
- 3
0
Hi All,
Just asking on how to deal change orders. Change order on Tiles (Addition) was approved already by us (Client).
Contractor sent us a notice that this Change Order has a procurement of 40 days and required 2 days installation.
This could be a potential delay, now my question is how can we incorporate this in the schedule?
Thanks in advance!
Dimple
2 replies
Oldest firstLog in or join to reply