Transferring of Activity Progress
- Created
- 0
- 4
Hi,
Im having problems on importing activity progress from my "Progress File" to my "Working File". I've tried doing the "P6 to Excel to P6" importing/exporting method.
In the process of exporting my "Progress File" to excel, I called out "Activity % Complete" as part of my excel template. Then, it reflected as "(*) Activty % Complete (%)" on the excel spreadsheet. it was mentioned in the forums changes made on those with asterrisks (*) will not be reflected once imported back to P6.
Can you guys suggest any method/s on how to work around this?
THANK YOU VERY MUCH!
btw, I'm using P6 V6.0
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?