Rough Estimate for 1 Residential Building 1 Electrician / floor

Dura CellMember for 15 years 10 months
Created
3
2
0

Dear All,

For those experience planners, is it possible for 1 electrician + labor / floor to work on residential bldg? 
I am working on rough estimate of manhours on site.

Thanks PP members
 

3 replies

Oldest first
  1. 0
    Konstantinos Parsalidis ·

    Hi there!Of course it would

    Hi there!

    Of course it would be, it all depends what they needed to install, how they would do the work, and how much time they'd have to do it...

    Regards,

    Konstantinos

  2. 0
    Andrew Pearce ·

    You need to consider the

    You need to consider the number of residential units on each floor.

    for a simple approximation for a 2bed unit I would allow 2man day to 1st Fix (conduit & wiring prior to plaster), 1 man day 2nd fix fittings & db, 1 man day Final fix, 1 man day test & commission.

  3. 0
    Hannan Mohammed Abdul ·

    Hi,I would like to prefer the

    Hi,

    I would like to prefer the Electrical works to be divided to 1st, 2nd & Final Fix.

    for 1st Fix (Embedded items in the slab)-2 Electricians and 4 Helpers

    for 2nd Fix(Embedded items in walls and fixtures)-3 Electricians and 6 Helpers

    for Final Fix -1 Electrician and 2 Helpers

     

    Always consider 2 Helpers with 1 Electrician.

     

     

    Regards

    Abdul Hannan