Resource loading for multi-level structure with non-typical floors
- Created
- 3
- 4
Hi Guys,
How do you usually do this.
We will build a 3 levels podium RC structure with 2 basement, so over all 5 levels. Each level has a different wall layout plan & floor framing plan, so there will be no levels with the same quantity of material resources. Contruction programme was made, just a typical construction programme, start from lowest level going to upper levels. And also, each level was divided into bays to determine concrete pouring sequence. It is like this:
Level B2 - Zone 1, Zone 2, etc. (activities further divided into walls/columns & slabs/beams)
Level B1 - Zone 1, Zone 2, etc.
I need to put material resources in the programme, let us say formwork, rebar and concrete. I refer to the BQ but in the BQ it shows the quantity of each resources as a total, it says how many cubic of concrete for beams, for walls, for columns, etc.
What will be the easiest way to load resources for each activity in my programme? Do I need to really compute the quantity for each bay of each level?
It is usually easy to do this for a high-rise RC structure with typical floors. But with non-typical floors like this, with a large floor area, how to do this.
Thanks guys.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?