When importing programme to P6 from MS project ,how to assign the baseline
In the Open Standard
Rinet SebastianMember for 13 years 11 months
- Created
- 2
- 2
0
Hi All,
I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to this takes a lot of time.
Is there a quick way to fix this.
Comments and help appreciated from everybody.
Thanks,
Rinet
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?