When importing programme to P6 from MS project ,how to assign the baseline

Rinet SebastianMember for 13 years 11 months
Created
2
2
0

Hi All,

I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to this takes a lot of time.

Is there a quick way to fix this.

Comments and help appreciated from everybody.

Thanks,
Rinet

2 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Rinet I'm afraid there is

    Hi Rinet

    I'm afraid there is no other way, due to the different concepts of baselining.

    MSP: Some fields added to the plan

    P6: A complete copy of the the project.

    I didn't check, but it should be possible to use the user defined fields to keep the information.

     

    Good Luck!

    Dieter

  2. 0
    Rinet Sebastian ·

    Hi Dieter, Thanks for the

    Hi Dieter,

    Thanks for the reply.I am not quite clear about the user defined fields.If you don't mind can you explain me how to do the user defined fields for importing to P6 and assigning the baseline for MSP programme.

    Thanks,

    Rinet 