Linear Scheduling

Michael MorrisonMember for 14 years 9 months
Created
1
3
0

Hi All,

Does anyone have a copy of an Excel sheet that can perform Linear Scheduling for road works (pipe line, drainage and resurfacing) of a busy street?

If you do kindly email it to use private messaging Cheers,

Michael

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Michael - Welcome to

    Hi Michael - Welcome to Planning Planet

    It is very easy to set one up using X - Y graphics.

    Pretty to look at but no criticality.

    Better to invest in proper software such as tilos or Asta Power project that has a Time Chain display facility.

    Best regards

    Mike Testro