Number of days problem
In the Open Standard
Siva GaneshMember for 14 years 10 months
- Created
- 4
- 4
0
Hello friends,
I have a small problem regarding the number of duration for activities.
Example:
Activity 1 has the original duration as 5 days. but the dates are as follows,
Start -- 20 feb 2013
Finish -- 25 feb 2013
But if we count the number of days, it actually 6 days..
I need finish date should be 24 feb 2013.
1st day -- 20 feb 2013
2nd day -- 21 feb 2013
3rd day -- 22 feb 2013
4th day -- 23 feb 2013
5th day -- 24 feb 2013
is it any setting problem??? please help me to sort out.
Thanks,
Sivaganesh