Skip to content

Progress Line

David CraigMember for 17 years 1 month
Created
3
14
0

Hello,

I was just wondering if somebody would be so kind as to provide information on progress lines? e.g purpose, how to read them etc.

Many thanks in advance,

David

3 replies

Oldest first
  1. 0
    Abilash Palakkadan Mathew ·

    progress line provides

    progress line provides indication (delayed / ahead or as planned) aganist each activity with resoect to the date set, either current date or project status date

  2. 0
    Mike Testro ·

    Hi David The progress line is

    Hi David

    The progress line is the point in time when the progress of the work was estimated - usually on a % complete basis.

    In most forms of software the percentage complete for each task is set in a "Progress Column" and the progressed section on the task bar is shown with some sort of undeline.

    Tasks with progress added fall to the left of the Progress Line (or Data Date in some cases) and those uncompleted tasks fall to the right.

    Only tasks on the right will respond to a re-schedule.

    Part completed task will be split and only the uncompleted section will remain in the programme logic.

    In Asta PowerProject you have the option to "Link Around Completed Tasks" which retains the out of sequence completion logic.

    SS Links with lead lags and no end of task successor lose all logic once the lead lag link is passed by the progress line - this is why only FS links should be used.

    If you have resources set to a work pattern make sure that the Time on the Progress line is earlier than the work pattern start time other wise you could lose an hour or two on each update.

    Finally there are two options with a progress line:

    1. ZigZag - which moves left to right showing which tasks are behind or ahead of programme.

    2. Straight - which after F9 shows the projected completion date as at the Progess Line.

    Remember always that Progress % is only a guess - compounded when multi task weightings are used.

    Best regards

    Mike Testro

  3. 0
    David Craig ·

    Thanks for the input

    Thanks for the input guys!!!!

    Very much appreciated.

    Regards,

    David

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?