Number of Helpers in man power histogram

Saju TSMember for 17 years 3 months
Created
1
3
0

How To fix the Numbder of Helper on Man power histogram, Other Man power like Steel fixer, Mason etc we fix based on their productivity on construction

Please let me know

1 reply

Oldest first
  1. 0
    Khaja Sharief ·

    It should be derived based on

    It should be derived based on the relative weightage in the overall manhours. It depends on the nature of activity. For example plastering work against 100 man-hours, you can distribute this manhours as 75% to Mason and 25% to Helper (Labors) i.e. the job requires 75 man- hours of Mason and 25 man-hours of Labor. 