Skip to content

Activity Relationships

Richard DayMember for 18 years 3 months
Created
1
2
0

The contractor has several activities that are tied to its successor with both an fs and ff ties. Activity 1 – 7/08/13 – 7/10/13   Activity 2 - 7/10/13 – 7/12/13. No lags on either relationship. Would this cause the activity to act like it has a fs-1 relationship?

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi Richard What you have is a

    Hi Richard

    What you have is a ladder effect which is common in manufacturing but has no real place in construction.

    It should make no difference to the operation of the logic and it could be beneficial when a progress up date goes beyond the SS link.

    Best regards

    Mike T.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?