Change Nonlabour to Labor in P6

Francis DominicMember for 14 years 6 months
Created
1
2
0

Hi all,

Is it possible to change assigned nonlabor to labor with the help of global change / or any other way?

Dominic

1 reply

Oldest first
  1. 0
    Abilash Palakkadan Mathew ·

    You can use global change or

    You can use global change or resource replacement options, it your resource assignment doesn't have actual values. Otherwise you will have to remove the actual values by keep the record somewhere else and then replace the resource with new one then put the actual as before.

Log in or join to reply