daily target

Ronron MartinezMember for 16 years 10 months
Created
1
5
0
Dear All Due to project delay the client have prepare their own schedule as per the remaining work divided to duration of 14 weeks. therefore client come out the daily target however I have concern on the other activity if the activity 1 example cannot meet the daily target then other activity will also affected is this the write method for planning. any advise Regards Ronron

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi RonronThis is unusual -

    Hi Ronron

    This is unusual - unles you have been asked to prepare a recovery schedule and you have failed to issue it.

    Normally the Employer cannot instruct you to work to his programme - it could be constructive acceleration and cost the Employer a lot of money.

    When you get your EoT in place the problem may go away.

    Best regards

    Mike Testro