Skip to content

P6 scheduling help

Andrew FrancisMember for 13 years 1 month
Created
3
4
0

hello - hope someone can help - I am new to primavera planning with P6 and there is something i dont understand and would love some help-

 

P6 set up : fixed duration units/time - physical % - no resource assigned to any activity

scenario :

I have 3 activities all f-s linked with no constraints -and a DD set to aug 1st 

1st activity starts on the 1st and finishes on the 3rd -100 % c/t

2nd activity starts 4th ends 21st - 100% c/t

3rd activity starts 22nd with and end 29th Aug 10% complete

problem:

why does the 3rd activity "snap back" to be in line with activity 1 when I re scedule so it looks as though it starts on the 1st where as I would expected to start on the 22nd and (visually) follow the end of activity 2.

If i make activity 2 99% c/t activity 3 stays where i think it should be -

 

what am i not doing right -

 

thanks andy 

3 replies

Oldest first
  1. 0
    Kaif Mohsin ·

    Dear Andrew,First of all

    Dear Andrew,

    First of all understand the concept of 'Data Date'. It is the date up to which actual performance is reported and the date from which the remaining work or the future work is scheduled.

    Now, in your case, your are giving actual start and finish dates to the 1st and 2nd activities and start date for the 3rd one. So, when you are scheduling then the 3rd activity remainining start date is becoming 1st Aug, the same as your 'Date Date'.

    And when you are making the 2nd activity to be 99% complete (or any percent less than 100), the 3rd activity will remain on 22nd Aug, following the FS Link it has with the 2nd one.

    Hope it is clear to you now.

    Best Regards,

    Kaif Mohsin

  2. 0
    Gary Whitehead ·

    Andy, 1) You should not have

    Andy,

     

    1) You should not have any actual progress registered after your data date. Re-set your data date to the point up to which you are reporting progress (Maybe 23rd?)

    2) When a start or finish date has actualy happened (ie moved from a forecast to an actual date), you should be ticking the "actual" checkbox next to the dates in your activity details, and manually confirming the actual date.

     

    Does that fix it?

  3. 0
    Andrew Francis ·

    Hi gary - i suppose the

    Hi gary - i suppose the problem is I am not using the DD correctly -i have 800 tasks in variuos states not started to late and behind- with a few complete.

    i fi use the DD say to todays date then I know i will have to revisit every task to pull it back in to the finish date ( there are no reasources assigned) - i ddint want to be a slave to the schedule doing that every month - but if that what needs to be done then i will try

     

    thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?