Tracking the projects
- Created
- 0
- 2
I hope every one will be fine. I need some help form u guys , I am planning engineer in a plant services department which deals with oil and gas , petrochemical plant turnarounds. We do turnarounds which merely have 15 to 20 days. My organization is interested in cummulative progress of the day. What we do , we plan , load resources , distribute them on 20 days (Bell shape) and start tracking by exporting the manhours to excel and than create S curve.This is simple way of tracking I wanted to track the projects via baselines in primavera p6.
a. Once i assgn the baseline , how can i track the progress ?After entering the manual entries , should i need to schedule by applying actuals or by updating the schedule
b. Do i need to schedule everytime i update the porject ,so that i can have the finish date ?
c.If my actual work is not as per progress, e.g. i started the inspection of 2 vessels by giving them the finish to start relationship in basline, but in actual , it follows a start to start relationship..do i need to change the relationship while i am tracking the projects?
Regards
Mohsin
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?