Planned Monthly and Weekly Progress

Albert BalogoMember for 18 years 4 months
Created
2
2
0

Greetings!

Hi Planners,

I extracted the Planned monthly and Weekly progress in P6, but the percentages does not match at every end of the month. Weekly percentage is beat higher compared to monthly. All settings have been applied accordingly,  e.g. unit of time, resource analysis, and timescale. Anybody can explain this problem.

 

Regards

Albert

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi AlbertThere are 12 months

    Hi Albert

    There are 12 months and 52 weeks in a year - so the weekly progress will overlap the months end and show a lerger result.

    Best regards

    Mike Testro

  2. 0
    Albert Balogo ·

    Thanks Mike, I really

    Thanks Mike, I really appreciate your quick response.