Planned Monthly and Weekly Progress
In the Open Standard
Albert BalogoMember for 18 years 4 months
- Created
- 2
- 2
0
Greetings!
Hi Planners,
I extracted the Planned monthly and Weekly progress in P6, but the percentages does not match at every end of the month. Weekly percentage is beat higher compared to monthly. All settings have been applied accordingly, e.g. unit of time, resource analysis, and timescale. Anybody can explain this problem.
Regards
Albert
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?