Imported Material Resources Duration set to zero

Mohamed El TurkyMember for 13 years 5 months
Created
1
4
0

Hi Everyone, 

i just imported a programme, i discovered that duration of material resources are set to zero unlike the activities durations, any advice ?

Best regards,

1 reply

Oldest first
  1. 0
    Alain De leon ·

    check the activity type on

    check the activity type on the activity details -select task dependent

Log in or join to reply