Activity Finish Moving Ahead 1day

Ammar TauqeerMember for 13 years
Created
4
2
0

Hello,

There is a problem when i update the schedule and mark the activity as started my activity finish date automatically moves ahead. Example For an activity A my start date is 12.Oct.2013 and finish date is 15.oct.2013. When i update the schedule and move my data date to 13.Oct.2013 my finish date automatically moves to 16.Oct.2013 

4 replies

Oldest first
  1. 0
    Rafael Davila ·

    For started activities if you

    For started activities if you do no change remaining duration the finish date will usually be delayed after re-scheduling run to be DD+remaining duration unless any other reason such as out-of-sequence rules takes over and delays it even further. 

  2. 0
    Raymund de Laza ·

    The issue is related with

    The issue is related with Time of the day... When ever updating any activity, consider the time start and time finish of activity.

  3. 0
    Ammar Tauqeer ·

    Raymund de Laza from where i

    Raymund de Laza from where i can manage the time of an activity?

  4. 0
    Raymund de Laza ·

    Edit... User Preferences.....

    Edit... User Preferences..... Dates.... Under the Time Click the button beside the Format you wish to display Time on the Dates Columns.

Log in or join to reply