Problems change effect

Wael ElhajjMember for 18 years 8 months
Created
3
1
0

Dear All, 

I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals. 

the schedule early finish and early end dates seem the same. no effect on succesor activies . 

how can i over come this problem 

3 replies

Oldest first
  1. 0
    Ronald Winter ·

    Do you mean the Tool, "Apply

    Do you mean the Tool, "Apply Actuals" or "Update Progress" or are your referring to some other process? 

  2. 0
    Wael Elhajj ·

    ronald ,i imported a file

    ronald ,

    i imported a file from P3 

    any change to any activity is not affecting the rest of the project .. 

    i even changed the data date ... 

    nothing happened 

  3. 0
    Ronald Winter ·

    I am almost afraid to ask but

    I am almost afraid to ask but did you re-calculate the schedule?  P6 is not like MS Project in that the default setting is to not automatically re-calculate the schedule after any change.