Duration difference after exporting P6 to MPP

Vic NoztuaMember for 13 years 1 month
Created
2
4
0

Hi!

Please need help.

After exporting a P6 project to MPP, several activities durations are showing incorrect durations - however you tried to correct the start and finish dates the duration stays incorrect?

 

Thank you in advance!

2 replies

Oldest first
  1. 0
    Mark Sales ·

    Hi Vic,   There are several

    Hi Vic,

     

    There are several things that could cause that.

    Firstly, you may have working time in P6 which is non-working time in MS. Check your calendars, weekends, bank holidays etc.

    Also, has this occurred on LOE of summary bars? Th eimport process could alter these.

    If you have any further trouble, delete these few activities and then re-create them.

     

    Regards

     

    Mark

  2. 0
    Vic Noztua ·

    Hi Mark. Many thanks for the

    Hi Mark. Many thanks for the help. I just re-create the incorrect duration activities in MPP, and yes I believe too that calendars has something more to do with these problem. Have a good day.