Sequence of Work for Construction of Spillway

Eric AmagonMember for 12 years 11 months
Created
3
3
0

Hi guys,

 

Im badly in need of your help.

Can anyone give me anidea for the detailed sequence of work in construction of spillway.

it is 4-bay gated spillway. The length of spillway is 66.9m, height from the bottom of foundation is 32.0 meters, the width of the foundation is 46.4 meters. Distance between each other is 12.6 meters, and the width of the pier is 3.5 meters..

your quick response is appreciated...

 

thanks,

eric

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi EricStart from the bottom

    Hi Eric

    Start from the bottom and work up.

    Best regards

    Mike Testro

  2. 0
    Eric Amagon ·

    Hi mike, Do you a sample

    Hi mike,

     

    Do you a sample achedule there?

     

    Thanks..

    Eric

  3. 0
    Mike Testro ·

    Hi EricNot really.The

    Hi Eric

    Not really.

    The spillway is an integral part of the dam structure and the contuction usually follows the earth fill in stepped stages.

    The construction is not complex being a simple concrete trough usually going through ramped and horizontal stages.

    The design is crucial because of the rapidly flowing water over it which - if allowed to create air bubbles - will take up the concrete with a negative force and break it up - this is called "cavitation".

    A scale model in a lab will be needed to test the design to allow for that.

    I hope that helps.

    Best regards

    Mike Testro

Log in or join to reply