Advance Payment

Rinum KinsokMember for 12 years 9 months
Created
3
3
0

I have a Client and a Contractor both difficult to manage both don't adhere too much to the contract clauses due to some  kind of friendship .

 

My problem is the advance payment , the contractor included it  on his baseline schedule  on the critical path,is this ok , I never had a baseline with an advanced payment mentioned on it before.

3 replies

Oldest first
  1. 0
    Rafael Davila ·

    At home advanced payments to

    At home advanced payments to contractor are very rare, usually contractor installs, then bill and get paid 30 days after billing.

    It is not unusual that some equipment manufacturer require an advance letter of credit deposited on a bank before start manufacturing and the transfer of money is performed at shipping. The purchase contract is subject to delivery of money. 

    So it depends on your contract terms.

    http://www.ncconstructionnews.com/uncategorized/can-you-stop-work-for-nonpayment/?doing_wp_cron=1389381901.0831100940704345703125 

    http://www.sauerconstructionlaw.com/Articles/Article20.html

    I would be reluctant to accept such baseline, unfortunately baselines and baseline updates can be interpreted as a change in contract terms. I would argue the delay will happen only if there is breach of contract but mere non payment for some time does not represents breach of contract. To make assumptions can be very risky. 

  2. 0
    Gary Whitehead ·

    As Rafael says, it very much

    As Rafael says, it very much depends on contract & circumstances.

     

    I have worked on projects before where a subby could not fund the procurement of materials without an advance payment, hence this might reasonably be ppart of the critical path, so long as the contract ackowledged it.

     

    I have also worked with subcontractors who just outright refuse to do start any work without an advance payment (these tend to be subbies in a monopoly position, such as utility companies)

     

    Never had it with a principal contractor before, but if the contract states a payment will be made before any work commences, then I don't see why it should be treated any differently to any other client deliberable which may fall on the critical path (approval of design, provision of power, etc).

    If the contract is such that the contractor is not obliged to commence a critcal element of work until this payment is made, they are quite within their rights to include it in the critical path.

     

    Cheers,

     

    G

     

  3. 0
    Rinum Kinsok ·

    Thanks Gary and Rafael for

    Thanks Gary and Rafael for your replies .