Hi Mike & Sunil
As per the hammock or Level of Effort method you suggested, I believe that the hammock activity progress will be calculated based on the remaining duration and it may not match with the real drawings submitted and approved.
So I have the opinion that it can be calculated with EV method as follows;
1. Consider the budget of shop drawings as 60%for submittal and 40% for approval.
2.Create the WBS as below;
Shop Drawings Submission & Approval
Submission
Civil
Mech
Elect
and similar for Approval as well.
3. Assign the above said budget value for each activity.
4. While updating the project, input the progress value considering the revisions and approvals.
The updated programme will show the rolled-up summary.
Regards
Kannan