Total Float
In the Open Standard
Raza RazaMember for 12 years 7 months
- Created
- 2
- 1
0
Dear All,
I have received a shcedule from Contractor for review with activties having very high float like 260 days, 120 etc........same like free flaot is very high. Its 16 months project .
Is there any standard practice limit for activities could assign free float, total float or lag in schedule.
Also if I am reducing the duration of critical activties the mechanical completion date is going beyond the project mechanical completion date despit it shall be completed before,.....