Progress out of sequence

David GorskiMember for 25 years
Created
0
2
0

Looking for some insight.

I have three activities A, B, & C. activity B has started and is 5% complete. Activities A & C have finish to finish logic links to B with a 10 day lag.  Activity B then proceeds to another activity, say D, with a finish to start logic link.  Activities A & C have not started. When I run a schedule update the status indicates that I have progress out of sequence (POS) for activity B.  Activity A & C have important output that must be complete before B can be complete. Why the POS?